The voters of Escambia County initially approved a half-cent sales surtax for the school district facilities capital outlay needs in 1997 for a period of five years. The voters approved a second referendum extending the half-cent sales surtax an additional five years through December, 2007.
The projected revenue was anticipated at $14 million per annum with an equitable distribution between each of the five school districts within Escambia County.
Projects completed in the first five years of the half-cent sales tax program included a new school (Blue Angels Elementary), general renovations to our older schools, additions, sitework and safety improvements.
In addition to the original budgeted project list totaling $70 million, there were two reallocations of funds for additional projects which utilized additional funds from projects which were completed under budget, additional revenue collected above the projected revenue and from accrued interest. The following summarizes the first five year projects:
| Original projects scheduled |
56 projects |
$70 million |
| First reallocation of funds |
24 projects |
$18.7 million |
| Second reallocation of funds |
34 projects |
$10.4 million |
| Totals |
114 projects |
$99.1 million |
The second reallocated budgeted projects were approved by the Board on May 18, 2004.